Patratu Super Thermal Power Project Phase 1

A 2,400 MW first phase of a planned 4,000 MW super thermal power project at Patratu, developed as an NTPC-state joint venture.

Estimated cost
₹18,668 cr
Reported spend
Not available
Announced
25 May 2018
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The 3x800 MW Phase 1 has moved beyond earlier commissioning expectations and remains under construction.

Delayed
First target
Dec 2022
Current target
Dec 2025
Revised target
Not listed
Public relevance

Jharkhand electricity consumers, industry and the eastern regional grid.

Timeline

2 events
25 May 2018
Foundation stone laid

The Prime Minister laid the foundation stone for Patratu STPP.

31 Dec 2025
Commissioning watch

The project is tracked toward a revised commissioning window.

Risk notes

  • Large thermal EPC and environmental compliance risks
  • Coal logistics and commissioning dependencies