State / JVUrban MetroUnder ConstructionDelayed

Bengaluru Metro Phase 2

A large expansion of Namma Metro including extensions and new lines such as Yellow, Pink and other Phase 2 corridors.

Estimated cost
₹26,405 cr
Reported spend
Not available
Announced
30 Jan 2014
Last verified
1 May 2026
Schedule check

Compared with the first announced target

Phase 2 has opened in parts but several elevated and underground corridors crossed original completion windows.

Delayed
First target
Dec 2020
Current target
Dec 2026
Revised target
Not listed
Public relevance

Bengaluru commuters on Whitefield, Electronic City, Bannerghatta Road, Nagawara and extension corridors.

Timeline

2 events
30 Jan 2014
Phase 2 approved

The Union Cabinet approved Bengaluru Metro Phase 2.

25 Mar 2023
Whitefield section opened

Part of the eastern extension entered public operation.

Risk notes

  • Underground tunnelling and dense urban interfaces
  • Multiple package-level schedule slips

Official/public sources

Use these links to inspect the underlying public sources for project details and updates.

Citation quality snapshot
Source mix
2 sources · Government
Verification freshness
Fresh

Source-linked record. Review the linked sources before relying on a claim.

Last source review was 46 days ago; still inspect linked sources before relying on any material claim.

Claim coverage check
Cost / funding
Review needed

Cost, funding or spend claims are visible; add/label an official budget, sanction, tender, award, DPR or financial update source.

Schedule / timeline
Review needed

Timeline and target-date claims are visible; add/label a source that specifically supports the first target, current target or revised completion claim.

Current status
Covered

At least one source label or source type appears to support the current project status or update claim.

Linked source labels: PIB: Cabinet approval for Bengaluru Metro Phase 2