Agra Metro Rail Project
A two-corridor metro system for Agra serving tourism, heritage and urban transport nodes including Taj East Gate, Agra Fort and Sikandra.
Compared with the first announced target
Priority operations began but full completion moved beyond the first target year, so the project is delayed at full-corridor level.
Agra residents, tourists, Taj Mahal and heritage-zone visitors and daily commuters
Timeline
The Agra Metro project was approved.
Project construction was inaugurated.
Initial passenger operations began on the priority stretch.
Risk notes
- Heritage-city underground works
- Full corridor delivery remains after priority opening
- Traffic and utility management in dense areas
Official/public sources
Use these links to inspect the underlying public sources for project details and updates.
Source-linked record. Review the linked sources before relying on a claim.
Last source review was 46 days ago; still inspect linked sources before relying on any material claim.
Cost, funding or spend claims are visible; add/label an official budget, sanction, tender, award, DPR or financial update source.
Timeline and target-date claims are visible; add/label a source that specifically supports the first target, current target or revised completion claim.
At least one source label or source type appears to support the current project status or update claim.
Linked source labels: PIB: Agra Metro approval and launch updates
Some links are broad homepages, sections, or aggregators. They remain visible for transparency, but should be refreshed to exact releases, tenders, PDFs, dashboard pages or articles before using them as final evidence.
- medium priorityPIB: Agra Metro approval and launch updates
Generic homepage or section URL; prefer the exact project page, release, tender, PDF, order, dashboard view or article URL.