Nagpur Metro Rail Project Phase 1

A two-corridor metro network in Nagpur implemented by Maha Metro, with Phase 1 fully inaugurated in 2022.

Estimated cost
₹8,680 cr
Reported spend
Not available
Announced
20 Aug 2014
Last verified
1 May 2026
Schedule check

Compared with the first announced target

Phase 1 completion occurred in December 2022 after pandemic and project execution delays.

Completed Late
First target
Dec 2020
Current target
Dec 2022
Revised target
Not listed
Public relevance

Nagpur commuters using north-south and east-west metro corridors and feeder networks.

Timeline

2 events
7 Mar 2019
First section opened

Initial Nagpur Metro services were inaugurated.

11 Dec 2022
Phase 1 completed

Remaining Phase 1 sections were dedicated to the nation.

Risk notes

  • Completed phase; residual concerns are ridership and integration
  • Extensions are separate future risks