Mumbai Metro Line 3 / Aqua Line

A 33.5 km fully underground metro corridor from Colaba to Bandra-Kurla Complex and SEEPZ, also known as the Aqua Line.

Estimated cost
₹37,276 cr
Reported spend
Not available
Announced
27 Jun 2013
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The underground corridor opened in phases after depot, tunnelling, land and environmental delays pushed the full corridor beyond earlier targets.

Delayed
First target
Dec 2021
Current target
Dec 2025
Revised target
Not listed
Public relevance

Mumbai commuters across Colaba, BKC, airport and SEEPZ corridors, with interchange benefits across suburban and metro networks.

Timeline

2 events
1 Oct 2016
Civil works advanced

Main underground civil packages moved into execution.

7 Oct 2024
First phase opened

The Aarey-JVLR to BKC stretch opened for public service.

Risk notes

  • Balance underground commissioning and station integration
  • Depot, systems and passenger ramp-up risks

Official/public sources

Use these links to inspect the underlying public sources for project details and updates.

Citation quality snapshot
Source mix
2 sources · Government
Verification freshness
Fresh

Source-linked record. Review the linked sources before relying on a claim.

Last source review was 46 days ago; still inspect linked sources before relying on any material claim.

Claim coverage check
Cost / funding
Review needed

Cost, funding or spend claims are visible; add/label an official budget, sanction, tender, award, DPR or financial update source.

Schedule / timeline
Covered

At least one source label or source type appears to support schedule, target, completion or timeline claims.

Linked source labels: PIB: Mumbai Metro Line 3 phase opening

Current status
Review needed

Current status is visible; add/label a recent official, tender, credible news, dashboard or public update source.