State / JVRenewable EnergyUnder ConstructionOn Track
Khavda Renewable Energy Park
A very large renewable energy park in Kutch combining solar and wind resources with phased generation and transmission infrastructure.
Estimated cost
₹1,50,000 cr
Reported spend
Not available
Announced
15 Dec 2020
Last verified
1 May 2026
Schedule check
Compared with the first announced target
The park is being executed in phases toward a 2030-scale renewable buildout; individual developers should be tracked package-wise.
First target
Dec 2030
Current target
Dec 2030
Revised target
Not listed
Public relevance
Renewable power consumers, grid operators, green industry, local workers and clean-energy supply chains
Timeline
3 events
15 Dec 2020
Large RE park plans advanced
Gujarat advanced the Kutch renewable energy park concept.
31 Dec 2024
Initial capacity additions
Major developers reported construction and initial commissioning activity.
31 Dec 2030
Long-term buildout horizon
Full-scale renewable capacity buildout is tracked toward 2030.
Risk notes
- Transmission evacuation is critical
- Harsh desert construction and O&M conditions
- Land, ecology and community interface risks
Official/public sources
Use these links to inspect the underlying public sources for project details and updates.