Dholera Special Investment Region and Industrial Smart City

A flagship Delhi-Mumbai Industrial Corridor node planned as a greenfield industrial smart city with trunk infrastructure, industrial land and urban services.

Estimated cost
₹3,000 cr
Reported spend
Not available
Announced
1 May 2009
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The activation area and trunk infrastructure have taken longer than early smart-city expectations; full buildout is long-term and phased.

Delayed
First target
Dec 2025
Current target
Dec 2030
Revised target
Not listed
Public relevance

Manufacturing investors, logistics users, workers and planned industrial-city residents in Gujarat

Timeline

3 events
1 May 2009
SIR framework advanced

Dholera was notified and integrated with DMIC planning.

1 Jan 2016
Activation area works started

Trunk infrastructure packages for the activation area began execution.

31 Dec 2024
Industrial allotments continue

Investor allotments and manufacturing proposals continued alongside trunk-infrastructure works.

Risk notes

  • Anchor tenant conversion is essential
  • Long greenfield city gestation
  • Transport links, utilities and land monetization must mature together