State / JVAirportUnder ConstructionDelayed
Dholera International Airport
A greenfield airport being developed to serve Dholera Special Investment Region and its industrial/logistics ecosystem.
Estimated cost
₹1,305 cr
Reported spend
Not available
Announced
14 Jun 2022
Last verified
1 May 2026
Schedule check
Compared with the first announced target
The airport has moved beyond earlier near-term public targets and is tracked as delayed until commissioning evidence is available.
First target
Dec 2025
Current target
Dec 2026
Revised target
Not listed
Public relevance
Dholera SIR investors, Ahmedabad region passengers, cargo users and Delhi-Mumbai Industrial Corridor logistics networks
Timeline
3 events
14 Jun 2022
Cabinet approval
The Union Cabinet approved Phase 1 development of Dholera International Airport.
1 Jan 2024
Construction progressed
Airport works progressed alongside the Dholera industrial-city build-out.
31 Dec 2026
Tracked commissioning window
Completion is tracked against a revised public delivery window.
Risk notes
- Airport demand depends on Dholera SIR ramp-up
- Road/utility and aviation approvals must remain synchronized
- Greenfield airport execution risk
Official/public sources
Use these links to inspect the underlying public sources for project details and updates.