State / JVSuburban RailUnder ConstructionOn Track

Bengaluru Suburban Rail Project

A 148.17 km suburban rail network for Bengaluru, divided into four corridors and largely aligned with existing railway corridors to improve commuter mobility.

Estimated cost
₹14,615 cr
Reported spend
Not available
Announced
7 Oct 2020
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The current tracked target remains 2026; this should be reconciled with corridor-wise updates as new official progress data is added.

On Track
First target
Dec 2026
Current target
Dec 2026
Revised target
Not listed
Public relevance

Bengaluru urban and suburban commuters across four rail corridors

Timeline

2 events
1 Sept 2021
DPR published on KRIDE site

Detailed Project Report uploaded to KRIDE project page.

1 Oct 2025
Project documentation continues

KRIDE page lists environmental and social documentation for corridor works.

Risk notes

  • Railway-interface complexity
  • Land, tree, environmental and urban-construction dependencies
  • Original DPR schedule requires updated reconciliation with current progress