State / JVAirportUnder ConstructionDelayed
Noida International Airport, Jewar Phase 1
A greenfield international airport at Jewar planned as a major NCR aviation and cargo hub with phased terminal and runway expansion.
Estimated cost
₹10,056 cr
Reported spend
Not available
Announced
25 Nov 2021
Last verified
1 May 2026
Schedule check
Compared with the first announced target
Phase 1 commercial opening moved beyond the earlier 2024 target, so it is tracked as delayed until operations begin.
First target
Dec 2024
Current target
Dec 2025
Revised target
Not listed
Public relevance
NCR passengers, western Uttar Pradesh businesses, air cargo users and Yamuna Expressway industrial region
Timeline
3 events
7 Oct 2020
Concession agreement signed
The airport concession was signed with the Zurich Airport-led concessionaire.
25 Nov 2021
Foundation stone laid
Prime Minister laid the foundation stone for the airport.
31 Dec 2025
Tracked opening window
Phase 1 commercial operations are tracked in the revised commissioning window.
Risk notes
- Airport certification and airline-readiness dependencies
- Surface connectivity must keep pace
- Future phases require land and demand realization
Official/public sources