Bundelkhand Expressway

A 296 km expressway connecting Chitrakoot with the Agra-Lucknow Expressway near Etawah, supporting Bundelkhand connectivity.

Estimated cost
₹14,850 cr
Reported spend
Not available
Announced
29 Feb 2020
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The expressway opened in July 2022 after a modest shift from the earlier delivery expectation.

Completed Late
First target
Feb 2022
Current target
Jul 2022
Revised target
Not listed
Public relevance

Bundelkhand residents, agriculture and freight users, defence corridor nodes and road travellers to the Agra-Lucknow Expressway.

Timeline

2 events
29 Feb 2020
Foundation stone laid

The Prime Minister laid the foundation stone.

16 Jul 2022
Inaugurated

The expressway was inaugurated for public use.

Risk notes

  • Completed asset
  • Operational risks include pavement maintenance and safety