Bundelkhand Expressway

A 296 km expressway connecting Chitrakoot with the Agra-Lucknow Expressway near Etawah, supporting Bundelkhand connectivity.

Estimated cost
₹14,850 cr
Reported spend
Not available
Announced
29 Feb 2020
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The expressway opened in July 2022 after a modest shift from the earlier delivery expectation.

Completed Late
First target
Feb 2022
Current target
Jul 2022
Revised target
Not listed
Public relevance

Bundelkhand residents, agriculture and freight users, defence corridor nodes and road travellers to the Agra-Lucknow Expressway.

Timeline

2 events
29 Feb 2020
Foundation stone laid

The Prime Minister laid the foundation stone.

16 Jul 2022
Inaugurated

The expressway was inaugurated for public use.

Risk notes

  • Completed asset
  • Operational risks include pavement maintenance and safety

Official/public sources

Use these links to inspect the underlying public sources for project details and updates.

Citation quality snapshot
Source mix
2 sources · Government
Verification freshness
Fresh

Source-linked record. Review the linked sources before relying on a claim.

Last source review was 46 days ago; still inspect linked sources before relying on any material claim.

Claim coverage check
Cost / funding
Review needed

Cost, funding or spend claims are visible; add/label an official budget, sanction, tender, award, DPR or financial update source.

Schedule / timeline
Review needed

Timeline and target-date claims are visible; add/label a source that specifically supports the first target, current target or revised completion claim.

Current status
Covered

At least one source label or source type appears to support the current project status or update claim.

Linked source labels: PIB: Bundelkhand Expressway inauguration