Zojila Tunnel Project
A strategic all-weather tunnel and approach road project on NH-1 near Zojila Pass to connect Kashmir Valley and Ladakh through difficult Himalayan terrain.
Compared with the first announced target
Latest official status cited in the record keeps the scheduled completion date at 29 September 2026, matching the tracked target.
Srinagar-Kargil-Leh travellers, defence logistics and Ladakh connectivity
Timeline
MoRTH signed an MoU for construction of Zojila Tunnel with capital cost around ₹6,808.69 crore.
Prime Minister marked commencement of work on Zojila Tunnel.
PIB reported ₹6,809.69 crore project cost, 52.13% physical progress and scheduled completion on 29 September 2026.
Risk notes
- High-altitude Himalayan tunnelling
- Severe weather and geological risk
- Strategic construction with seasonal constraints
Official/public sources
Use these links to inspect the underlying public sources for project details and updates.
Source-linked record. Review the linked sources before relying on a claim.
Last source review was 46 days ago; still inspect linked sources before relying on any material claim.
Cost, funding or spend claims are visible; add/label an official budget, sanction, tender, award, DPR or financial update source.
At least one source label or source type appears to support schedule, target, completion or timeline claims.
Linked source labels: PIB: Zojila Tunnel project status and completion target
At least one source label or source type appears to support the current project status or update claim.
Linked source labels: PIB: Zojila Tunnel project status and completion target