Sela Tunnel Project
A strategic tunnel system on the Balipara-Charduar-Tawang road that improves all-weather access to Tawang and reduces snowbound pass exposure.
Compared with the first announced target
The high-altitude tunnel was inaugurated in March 2024 after moving beyond earlier public delivery windows.
Tawang region residents, border-area logistics, tourism and strategic road users needing all-weather connectivity.
Timeline
Foundation stone laid for tunnel connectivity toward Tawang.
The project was inaugurated as a strategic all-weather connectivity asset.
Risk notes
- Completed high-altitude project
- Ongoing operational risk from snow, landslides and road maintenance
Official/public sources
Use these links to inspect the underlying public sources for project details and updates.
Source-linked record. Review the linked sources before relying on a claim.
Last source review was 46 days ago; still inspect linked sources before relying on any material claim.
Cost, funding or spend claims are visible; add/label an official budget, sanction, tender, award, DPR or financial update source.
Timeline and target-date claims are visible; add/label a source that specifically supports the first target, current target or revised completion claim.
At least one source label or source type appears to support the current project status or update claim.
Linked source labels: PIB: Sela Tunnel inauguration details