Pune Ring Road

A large greenfield ring road planned around the Pune Metropolitan Region to decongest the city and connect industrial/logistics corridors.

Estimated cost
₹42,711 cr
Reported spend
Not available
Announced
1 Jan 2021
Last verified
1 May 2026
Schedule check

Compared with the first announced target

Land acquisition, cost escalation and package readiness have pushed the project beyond earlier delivery expectations, so it is tracked as delayed.

Delayed
First target
Dec 2026
Current target
Dec 2028
Revised target
Not listed
Public relevance

Pune metropolitan commuters, industrial freight, logistics operators and bypass traffic across Mumbai, Nashik, Solapur and Satara corridors

Timeline

3 events
1 Jan 2021
Approvals and land acquisition advanced

MSRDC advanced land acquisition and project preparation.

1 Jan 2024
Cost escalation and package preparation

Public reporting showed increased cost and package/tender activity.

31 Dec 2028
Tracked revised window

The project is tracked against a later construction window.

Risk notes

  • Large peri-urban land acquisition
  • High capital cost and escalation
  • Environmental/local opposition and utility shifting