StateUrban RoadsPartly OperationalDelayed
Mumbai Coastal Road Project, South Section
A coastal urban road from Marine Drive to Worli with tunnels, interchanges and reclaimed-road sections to reduce travel time along south Mumbai’s western seafront.
Estimated cost
₹13,984 cr
Reported spend
Not available
Announced
1 Oct 2018
Last verified
1 May 2026
Schedule check
Compared with the first announced target
The project opened in phases after the earlier target and still requires final connectors/works, so it is delayed.
First target
Dec 2022
Current target
Dec 2025
Revised target
Not listed
Public relevance
Mumbai commuters, emergency services, public transport users and western corridor road traffic
Timeline
3 events
1 Oct 2018
Construction started
BMC began major works after approvals.
11 Mar 2024
First section opened
Initial Coastal Road sections opened for public use.
31 Dec 2025
Tracked finishing window
Remaining connectors and public-realm works are tracked.
Risk notes
- Marine works and traffic-interface complexity
- Environmental litigation history
- Connector integration with Sea Link and city roads remains important