Mumbai Coastal Road Project, South Section

A coastal urban road from Marine Drive to Worli with tunnels, interchanges and reclaimed-road sections to reduce travel time along south Mumbai’s western seafront.

Estimated cost
₹13,984 cr
Reported spend
Not available
Announced
1 Oct 2018
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The project opened in phases after the earlier target and still requires final connectors/works, so it is delayed.

Delayed
First target
Dec 2022
Current target
Dec 2025
Revised target
Not listed
Public relevance

Mumbai commuters, emergency services, public transport users and western corridor road traffic

Timeline

3 events
1 Oct 2018
Construction started

BMC began major works after approvals.

11 Mar 2024
First section opened

Initial Coastal Road sections opened for public use.

31 Dec 2025
Tracked finishing window

Remaining connectors and public-realm works are tracked.

Risk notes

  • Marine works and traffic-interface complexity
  • Environmental litigation history
  • Connector integration with Sea Link and city roads remains important