Transmission System for Evacuation of 13 GW Renewable Energy from Ladakh

A high-capacity transmission corridor to evacuate 13 GW of renewable energy from Ladakh to the national grid through challenging high-altitude terrain.

Estimated cost
₹20,774 cr
Reported spend
Not available
Announced
18 Oct 2023
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The Cabinet-approved long-horizon transmission project is tracked as on track until public implementation evidence shows slippage against the FY 2029-30 window.

On Track
First target
Mar 2030
Current target
Mar 2030
Revised target
Not listed
Public relevance

Renewable power developers, national grid users and clean-energy consumers across India

Timeline

3 events
18 Oct 2023
Cabinet approval

The Union Cabinet approved the transmission system for 13 GW renewable evacuation from Ladakh.

1 Jan 2024
Planning and implementation preparation

Central transmission agencies moved toward detailed execution planning.

31 Mar 2030
Approved delivery horizon

The project is tracked to the Cabinet-approved FY 2029-30 horizon.

Risk notes

  • Extreme altitude and long-distance HVDC execution
  • Right-of-way and environmental constraints
  • Renewable project synchronization risk