CentralPower TransmissionUnder ConstructionOn Track
Transmission System for Evacuation of 13 GW Renewable Energy from Ladakh
A high-capacity transmission corridor to evacuate 13 GW of renewable energy from Ladakh to the national grid through challenging high-altitude terrain.
Estimated cost
₹20,774 cr
Reported spend
Not available
Announced
18 Oct 2023
Last verified
1 May 2026
Schedule check
Compared with the first announced target
The Cabinet-approved long-horizon transmission project is tracked as on track until public implementation evidence shows slippage against the FY 2029-30 window.
First target
Mar 2030
Current target
Mar 2030
Revised target
Not listed
Public relevance
Renewable power developers, national grid users and clean-energy consumers across India
Timeline
3 events
18 Oct 2023
Cabinet approval
The Union Cabinet approved the transmission system for 13 GW renewable evacuation from Ladakh.
1 Jan 2024
Planning and implementation preparation
Central transmission agencies moved toward detailed execution planning.
31 Mar 2030
Approved delivery horizon
The project is tracked to the Cabinet-approved FY 2029-30 horizon.
Risk notes
- Extreme altitude and long-distance HVDC execution
- Right-of-way and environmental constraints
- Renewable project synchronization risk
Official/public sources
Use these links to inspect the underlying public sources for project details and updates.