Atal Tunnel, Rohtang

A 9.02 km all-weather highway tunnel below Rohtang Pass, reducing the Manali-Leh route and improving strategic connectivity to Lahaul-Spiti and Ladakh.

Estimated cost
₹3,200 cr
Reported spend
Not available
Announced
28 Jun 2010
Last verified
1 May 2026
Schedule check

Compared with the first announced target

The tunnel opened in October 2020 after earlier construction targets slipped because of high-altitude geology, water ingress and winter working constraints.

Completed Late
First target
Dec 2016
Current target
Oct 2020
Revised target
Not listed
Public relevance

Residents of Lahaul-Spiti, travellers between Manali and Leh, defence logistics and tourism users requiring all-weather access.

Timeline

2 events
28 Jun 2010
Construction launch

Main works advanced under Border Roads Organisation for all-weather access beyond Rohtang Pass.

3 Oct 2020
Opened to traffic

The Prime Minister dedicated Atal Tunnel to the nation.

Risk notes

  • Completed project; residual risks are operations, safety and winter maintenance
  • High-altitude maintenance and traffic management remain important